Why "The Gander"?

Why "The Gander"?

Most people are familiar with the mythology of St. Martin's cloak. Less familiar may be the myth of St. Martin's goose. It is told that Martin the priest was wanted as bishop. He didn't want the job, and so hid (here the accounts are fuzzy) in a goose pen, barn, or bush and was revealed by the honking of the goose. A gander is a male goose - much like a drake is a male duck. To "take a gander" means to take a peek, a look. We hope to use this space to take a deeper look at things happening at St. Martin's, and share more thoughts and information with you.

Wednesday, October 17, 2018

Boiler Update: Mid-work

As we reported on September 13, the boiler that failed on us last December is currently undergoing replacement. This project continues on schedule. Here is what has happened over the last month: 

The Trefz Mechanical crew removed the defunct boiler in mid-September. In order to get the pieces out, they had to build a custom dolly, narrow enough to fit through the basement door. Incredibly, each section was removed by two men! 


Dumpster at St. Martin's
Custom cart made to haul the boiler components out of the basement
Old boiler components (800 lb. cast iron!) in dumpster, pending recycling
As mentioned in the previous message, the one boiler will be replaced with two compact and energy efficient boilers. A new concrete pad was set, and the new boilers have been installed.
Two new boilers on their concrete pad. Ever seen the inside of a boiler before?
Back/control side of new boilers.
New exhaust ducts are being installed to connect to the existing chimney. You can see the U-hangers in the photos above.

New piping set for installation.

Jake and Kevin are assembling the new piping on site.
Important improvements included in the work are the introduction of more thermostats and valves, so that heating can be better-controlled to provide heat when and where it is needed in the Parish House - rather than the all-on-in-every-space as we have had in the past. The new boilers are 83% energy efficient (vs. 60-70% estimated efficiency of the old boilers), which will result in operating cost savings and support St. Martin's commitment to sustainability.


The Rev. Jarrett Kerbel explains the new control valves for zoned heating.
  
New thermostats have popped up around the building.
This work is estimated to be completed, with the church and parish house heated by the two new boilers, by mid-November. In the meantime, the remaining older boiler is being started up this week.

All will agree that this work is necessary and of obvious value to the parish, as it permits our buildings to be used. Yet, it should be noted, the work is difficult, and the components are expensive. The entire project will cost about $200,000, per the following cost breakdown:

Labor – $34,000
Material – $27,200
Electrical – $5,200
Insulation – $7,800
Control – $15,500
Major Equipment – $54,000 (The heat-exchanger is about $2,500. The rest is the two boilers and boiler control.)
Commissioning – $3,600 
Permitting (allowance) – $3,000
Contingency (allowance for unforeseen scope)* – $30,000
Engineering Fees – $24,800
Total: $205,100  

*note that it is hoped that $10,000 to $15,000 of the contingency will not need to be spent

Thank you for your patience during this time. We'll continue to keep you updated on our progress.

Blessings,
Dave Harrower, properties committee chair